San Giuliano Milanese Experiences Widespread Blackout, Civil Protection Steps In
Milan, June 21, 2026 – The municipality of San Giuliano Milanese, located just outside Milan, has been grappling with extensive power outages for two consecutive days, leaving thousands of residents without electricity. The prolonged blackout has severely impacted daily life, affecting not only homes but also critical services such as supermarkets, the municipal building, and the local police station.
Mayor Marco Segala has taken decisive action, convening the Civil Protection Coordination Center. In response to the isolation of municipal services due to the power failure, a dedicated mobile phone number has been activated for emergencies, ensuring residents can still reach authorities.
Structural Issues Identified as Cause of Outage
According to a statement from the municipality on its social media channels, the root of the problem is structural. “It has emerged that it is a structural problem: there are faults on three main connection lines to the distribution cabins,” the statement explained. Technicians from Duereti, the company managing electricity distribution, have reportedly identified the points of failure and are currently working on repairs. However, these repairs are expected to take several more hours.
The impact of the blackout extends beyond mere inconvenience. Mayor Segala highlighted the severe consequences for local businesses: “Without electricity, supermarkets and dozens of commercial establishments in the area have also been affected, and they will have to discard refrigerated food that has been without power for hours.” Furthermore, residents in buildings equipped with electric-powered water pumps (autoclaves) are now facing water shortages, adding another layer of difficulty to an already challenging situation.
Duereti Attributes Outage to Record Consumption Surge
Duereti issued a statement late Sunday afternoon, shedding light on the circumstances leading to the widespread outages. The company explained that “following the high temperatures recorded in recent days in the Milan metropolitan area – approximately 35 degrees Celsius – the maximum annual load on the electricity distribution networks managed by Duereti was registered, with a sudden 38% increase in consumption compared to last week.”
While Duereti typically resolves service interruptions quickly through its remote control system and on-site teams, the company noted that in cases of multiple faults, such as those experienced in San Giuliano Milanese, restoration times can be extended. “In such situations, to proceed with reactivation operations, it is necessary to send specialized technicians to the site to locate the points of intervention and to carry out excavation activities to uncover the section of the network to be repaired,” Duereti stated. The presence of parked cars, even on sidewalks, often necessitates the use of tow trucks to clear the area for repair work, further complicating and delaying efforts.
Duereti confirmed that its teams have been on site since Sunday night in San Giuliano Milanese, have identified the faults, and are actively engaged in repair work. The company anticipates that all affected users will have their power restored around 12:15 PM on Monday.
The prolonged power outage underscores the vulnerability of urban infrastructure to extreme weather conditions and the critical importance of reliable electricity supply for both residents and businesses.
Source: milano.corriere.it