Rome’s Incinerator Project Moves Forward: Mayor Gualtieri Signs Approval Order
Rome, Italy – In a pivotal development for the capital’s waste management strategy, Mayor and extraordinary government commissioner Roberto Gualtieri has signed the ordinance officially approving the incinerator project. This order certifies the positive conclusion of the service conference for the Rome incinerator project, issuing the regional/commissioner unified authorization (PAUR), environmental impact assessment (VIA), and integrated environmental authorization (AIA).
“Today we are taking a decisive step towards the realization of the incinerator, which will finally give Rome the ability to manage its waste autonomously,” stated Mayor Gualtieri.
Environmental Conditions and Prescriptions
The investigative work for the project concluded with the introduction of 11 environmental conditions and 97 specific prescriptions. According to the Capitoline administration, “The introduction of 11 environmental conditions and 97 prescriptions strengthens the project, the execution of which will be subject to verification by all competent bodies involved.”
A significant portion of these prescriptions will need to be incorporated during the executive design phase, which the proponent is expected to complete within the next 30 days. Other directives will be relevant to the plant’s operational management phase.
What This Means for Rome’s Waste Management
This approval marks a critical juncture for Rome, which has long grappled with waste disposal challenges. The incinerator is envisioned as a key component in achieving greater independence in waste management, reducing reliance on external facilities and potentially addressing issues such as overflowing bins, particularly during holiday periods, and the region’s low recycling rates.
Key Takeaways:
- Official Approval: Mayor Roberto Gualtieri has signed the ordinance, giving the green light to the incinerator project.
- Comprehensive Authorization: The project has received PAUR, VIA, and AIA approvals.
- Environmental Safeguards: 11 environmental conditions and 97 prescriptions have been integrated into the project.
- Next Steps: The executive design phase, incorporating the new prescriptions, is expected within 30 days.
- Goal: To enable Rome to manage its waste autonomously and improve overall waste management efficiency.
Background and Related Issues
The path to approving the incinerator has not been without its complexities. Previous reports have highlighted challenges such as Lazio’s position as one of the last regions in Italy for separate waste collection and a significant deficit in waste treatment plants. There have also been investigations by the Court of Auditors into the appointments of managers related to the project, raising concerns about potential waste of public funds.
The approval of the incinerator at Santa Palomba follows earlier steps, including the commencement of the permit process and the handover of the area to the concessionaire, signaling a sustained effort to bring this project to fruition.